Corunna water tower painted wrong color; city will recoat it

The engineer's Oct. 20 report in Monday's council packet also says the FAA now wants another study of the tank's height, which could affect the pressure it delivers.

Corunna's new elevated water storage tank was painted the wrong color, and the city has decided to have it recoated in the color it was supposed to be. That is in the engineer's latest progress report, included in the packet for Monday's 7 p.m. City Council meeting in the lower level of the Community Center, 457 Emma Drive.

"Contractor for the elevated water storage tank painted the tank the wrong color after providing the correct submittals," says Progress Report #25 from C2AE, dated Oct. 20 and covering Sept. 14 through Oct. 20 on the Corunna DWSRF FY2024 construction work. "The City has decided to proceed with recoating the structure with the originally intended color. This will end up requiring additional construction observation services." The report does not put a dollar figure on the recoating or say who absorbs it.

The same report flags something with more at stake for people on city water. The Federal Aviation Administration has told the engineers that another study is needed of the tank's height, a requirement the report says was triggered when the contractor started the crane permit. "Should this study come back and require the elevated water storage tank to be further lowered than the FAA required during design, this could be a significant value impact to the elevated water storage tank and the pressure it will be able to provide to the system," the report says.

All three construction contracts are behind. The report lists Dec. 15, 2025 milestone dates for the booster pump stations, the elevated tank and the water distribution work, all still "in progress," and says construction "has exceeded the originally contracted substantial completion dates." The Contract 1 contractor "will not likely be completing their work within the contract period," the Contract 2 contractor is "at risk" of the same, and the Contract 3 contractor has filed an extension-of-time request. On its own budget, C2AE reports using about 102% of its recently amended budget at 99% complete, and says an amendment has been submitted for more construction coverage.

The report also records a design change on Shiawassee Street roughly between Ferry Street and Oak Street: the proposed sidewalk is being lowered so road drainage keeps running west into the new storm system west of the existing duct bank.

The borrowing behind that work shows up in the draft audit council members take up Monday. The draft financial statements in the packet put the city's long-term obligations, including the current portion, at $7,369,127 as of June 30, 2026, up from $1,516,888 a year earlier, with $6,055,663 of the increase from draws on the 2024 Drinking Water State Revolving Fund loan. That $7,359,417 loan, dated Aug. 16, 2024, carries 2.00% interest and annual payments of $130,000 to $270,000 through April 1, 2064. The audit pages in the packet are stamped "Draft."

Charter votes, and ball fields that stay ball fields

The packet's communications include results on the city's three November ballot questions. Charter Amendment 4.2 passed 563-549, or 50.63%. Charter Amendment 5.2 passed 596-502, or 54.28%. The gender neutral ballot language proposal failed, 538 yes to 635 no.

Monday's consent agenda also carries the Oct. 19 minutes, which record a decision years in the making for the Pine Street ball fields. Council voted 5-0 to adopt the 2026-2031 Parks and Recreation plan while rejecting the 2008 staff recommendation that fields two and three be held for future cemetery expansion. Brian DeLorge moved and Mike Carr seconded; DeLorge, Helen Granger, Dan Ayers, Carr and Jaquelyn Rye are recorded voting yes, and Mayor Wayne LeDuc is listed as present without a recorded vote. City Manager Joe Sawyer told the hearing the 2008 plan flagged 30 to 40 years of cemetery lots still platted, that an effort to buy land from Caledonia Township by the airport for cemetery expansion "never came to" an agreement, and that this year's budget includes additional columbariums. The same meeting approved Traffic Control Order 243 5-0, with the stop sign moved to the southwest corner rather than the southeast; The Current reported in October that the order covers Development Drive and Parmenter Road.

What happens next

The agenda printed at the front of the packet lists four items of business Monday: the 2025/2026 audit presentation, 2027 council meeting dates, 2027 healthcare options and city HSA contributions. A Safe Routes to School agreement is not among the listed items, though The Current reported that the Corunna school board's Monday agenda asks the district to authorize a Safe Routes to School partnership with the city. The Oct. 19 minutes quoted here are the version up for approval Monday. The council's next regular meeting is Monday, Dec. 7.

The Morning Current. Free, daily, by 6 AM.

Every council vote, police report, and school decision in Shiawassee County — before your first coffee.